(A+B)’s one day work = (B+C)’s one day work = (C+A)’s one day work = (A+B+C)’s one day work = If A do work alone, then, A’s one day work = (A+B+C)’s one day work – (B+C)’s one day work 1/10 - 1/15 =(3-2)/30 =1/30 Thus, A can complete the work in = 30 days.